Well, no surprise, due to all the additional underpinning, archaeology and holidays, we're running about 9 weeks behind where we'd ideally be. The good news is that things are going up rather than down.
Yet another (motley!) collection of photos.
|
The base foundations which will be under the main slab. (0109) |
End gable rebuilt and the foundations. |
More shots of the foundations. |
|
Ten days later and the services start to be put in ready for the slab (1009) |
A better overall view of the site |
Sarah looking for the front door! Francis looking at the new species of Hampshire Blue Snake... |
|
Concrete poured at last (1609) |
|
|
|
Collar for the Well opening (750mm dia) |
Conduits into what will be the equipment cupboard - these are from the outside, others will be in the floor screed. |
|
|
Interesting mortice tool - like a mini chain saw. |
|
|
|
|